|
Activities completed during the week of
November 1,2004:
 | Worked on paperwork for kitchen
permits. |
 | Continued installation of door
glazing. |
 | Removed electrical materials. |
 | Patched asphalt driveway. |
 | Completed grading. |
 | Final fire inspection held for both
additions. |
|
11/11/2004
Media Center is
stocked and in use! |
11/11/2004
New computer lab...
up and running! |
|
Activities completed during the week of
October 11,2004:
 | Completed base molding for gym
floor. |
 | Continued working on programming of
ATC controls. |
 | Worked on paperwork for permits for
kitchen. |
 | Changed cores for interior doors. |
|
10/19/2004
Furniture and books set up in the new Media Center. |
10/19/2004
Equipment being installed in the new kitchen. |
|

10/19/2004
Floor sealed in new gymnasium.
|
10/19/2004
New computer lab completed. |
Activities completed during the week of
September 6, 2004:
 |
Continued connections of kitchen
equipment. |
 |
Commenced installation of light
fixtures in kitchen. |
 |
Completed installation and testing of
fire alarm devices. |
 |
Completed installation of acoustical
ceiling tiles. |
 |
Completed installation of interior
doors and glazing. |
 |
Commenced final cleaning. |
 |
Commenced start-up of classroom
Airedale units. |
 |
Obtained a Temporary Certificate of
Occupancy for Area A classrooms. |
|
9/10/2004
Another small instruction classroom prepared for use. |
9/10/2004
Furniture delivered to one of the new small instruction classrooms. |
9/10/2004
Main entrance completed. |
9/10/2004
Flooring delivered to new gymnasium. |
9/10/2004
Completed hallway leading to new classrooms. |
9/10/2004
Carpeting laid in Media Center. |
9/10/2004
Another classroom completed. |
9/10/2004
Furniture delivered to completed Art classroom. |
9/10/2004
Classroom completed.
|
|
Activities completed during the week of August 16,2004:
 | Completed site grading and
installation of curbs and sidewalks. |
 | Continued installation of kitchen
equipment. |
 | Continued installation of fire
alarm devices. |
 | Completed installation of floors in
renovated rooms. |
 | Commenced painting rooms. |
 | Completed installation of water
heaters in existing boiler room. |
 | Commenced installation of
acoustical ceiling tiles. |
 | Transferred permanent power. |
|
8/17/2004
Leveling of ground continues. |
8/17/2004
Book shelves assembled for Media Center. |
8/17/2004
Dry erase board and bulletin board installed in classroom. |
8/17/2004
Shelving and storage cabinet installed in classroom. |
8/17/2004
Cabinets and cubbies installed in classroom. |
8/17/2004
Basketball hoops installed in gymnasium. |
8/17/2004
Exterior work continues on gymnasium. |
8/17/2004
Doors to new main entrance are installed. |
|
8/17/2004
Cement poured for sidewalks. |
8/17/2004
Exterior work continues on the classroom addition. |
Activities completed during the week of June 14, 2004:
 | Power washed brick on classroom
wing. |
 | Continued installation of light
fixtures in gym. |
 | Continued installation of ceramic
floor tile. |
 | Continued demolition of existing
kitchen. |
 | Continued installation of roof
system and coping. |
 | Commenced pulling data wire. |
|
|
6/21/2004
Work on gymnasium wing continues. |

6/21/2004
Work on classroom wing continues.
|
Activities completed during the week of June 7, 2004:
 |
Continued installation of brick in
Area B. |
 |
Continued installation of light
fixtures in both construction areas. |
 |
Continued installation of ceramic
wall and floor tile. |
 |
Continued demolition of existing
kitchen. |
 |
Pulled secondary feeder wires. |
|
|
Activities completed during the week of June 1, 2004:
 |
Continued installation of brick in
Area B. |
 |
Commenced installation of light
fixtures in both construction areas. |
 |
Continued installation of ceramic
wall and floor tile. |
 |
Completed painting in classroom wing. |
 |
Commenced demolition of existing
kitchen. |
|
5/28/2004
Work continues on the interior of the new media center. |
5/28/2004
Tile installed in new restroom. |
|
5/28/2004
Classroom HVAC unit delivered. |
Activities completed during the week of May 17, 2004:
 |
Power washed brick. |
 |
Continued installation of brick on
gymnasium wing. |
 |
Installed interior HVAC units in new
classrooms. |
 |
Continued installation of electrical
wire and fixtures. |
 |
Continued installation of ceramic
wall tile in classrooms. |
 |
Commenced painting on gymnasium wing. |
|
Activities completed during the week of May 10, 2004:
 |
Continued installation of brick. |
 |
Commenced installation of brick on
gymnasium area. |
 |
Continued mechanical piping in
existing mechanical room. |
 |
Continued installation of electrical
wire and cable trays. |
 |
Commenced installation of ceramic
wall tile. |
|
|
5/14/2004
Brick face being installed. |
5/14/2004
Exterior block walls completed. |
Activities completed during the week of May 3, 2004:
 | Continued installation of brick. |
 | Complete installation of
underground conduit for transformer. |
 | Completed installation of pumps in
existing mechanical room. |
 | Continued ductwork in gym and
mechanical mezzanine. |
 | Completed flashing at perimeter of
roof additions. |
|
|
Activities completed during the week of
April 26, 2004:
 | Commenced installation of brick. |
 | Commenced excavation for power to
transformer location. |
 | Completed installation of
underground conduit for transformer. |
 | Installed pumps in existing
mechanical room. |
|
4/26/2004
Interior work on gymnasium continued. |
4/26/2004
Work continues on future hallway. |
4/26/2004
Interior work on gymnasium continued. |
Activities completed during the week of
April 12, 2004:
 |
Continued installation of masonry
walls. |
 |
Completed installation of electrical
masonry wall rough-ins. |
 |
Poured concrete slab for mezzanine in
gym area. |
 |
Poured concrete slab on grade for
kitchen. |
 |
Removed existing glass block in
Multi-Purpose Room and installed masonry block. |
 |
Connected new sanitary line to
existing area. |
 |
Commence pulling wire for devices in
classroom area. |
 |
Completed installation of mechanical
piping in existing corridor. |
|
Activities completed during the week of
April 5, 2004:
 |
Continued installation of masonry
walls. |
 |
Continued installation of electrical
masonry wall rough-ins. |
 |
Completed installation of mechanical
piping and duct work in classroom additions. |
 |
Completed installation of underground
plumbing and underground electric in kitchen area. |
 |
Installed new site pole at corner of
gymnasium site. |
|
|
Activities completed during the week of
March 29, 2004:
 |
Continued installation of masonry
walls. |
 |
Continued installation of electrical
masonry wall rough-ins. |
 |
Continued installation of mechanical
ductwork. |
 |
Continued installation of mechanical
piping. |
 |
Commenced installation of underground
plumbing in kitchen. |
 |
Removed hangover of existing gym. |
|
4/9/2004
Media Center is framed with block walls. |
4/9/2004
Exterior walls for gymnasium installed. |
|

4/9/2004
Exterior block walls continue to be installed.
|
Activities completed during the week of
March 22, 2004:
 |
Completed installation of masonry
walls. |
 |
Commenced installation of masonry
walls on gymnasium addition. |
 |
Completed installation of electrical
masonry wall rough-ins. |
 |
Commenced installation of electrical
masonry wall rough-ins on gymnasium addition. |
 |
Continued installation of mechanical
ductwork and mechanical piping for classroom additions. |
 |
Commenced layout of mechanical
ductwork in gymnasium addition. |
|
3/26/2004
Block wall installation continued. |
|

3/19/2004
Masonry walls installed.
|
Activities completed during the week of
March 8, 2004:
 | Continued installation of masonry
walls. |
 | Continued installation of
electrical masonry wall rough-ins. |
 | Completed installation of domestic
water piping insulation. |
 | Installed new Rooftop Unit above
mechanical room. |
|
3/15/2004
Work continues on masonry walls. |
|
3/15/2004
Concrete block on site for masonry walls of gymnasium.
|
Activities completed during the week of
February 16, 2004:
 |
Completed installation of roof
insulation and tar in Area A. |
 |
Commenced installation of roof
insulation and tar in Area B. |
 |
Continued installation of masonry
walls |
 |
Continued installation of electrical
masonry wall rough-ins. |
 | Completed installation of exhaust
fan roof curbs. |
 | Completed installation of wood
blocking for roof curbs. |
 | Commenced installation of domestic
water piping in chase walls. |
|
2/25/2004
Interior walls installation commenced. |
2/25/2004
Workers prepare to install interior walls. |
2/20/2004
Roof curbs installed. |
2/20/2004
Installation of roof commences. |
|

2/20/2004
Installation of concrete block walls commences.
|
Activities completed during the week of
February 9, 2004:
 |
Completed above ground plumbing pipe
and roof drain. |
 |
Completed above ground rood drain connections. |
 |
Commenced installation of masonry
walls. |
 |
Commenced installation of electrical
masonry wall rough-ins. |
 |
Completed installation of roof curbs. |
 |
Commenced installation of exhaust fan
roof curbs. |
 |
Commenced installation of wood
blocking for roof curbs. |
|
Activities completed during the week of
February 2, 2004:
 |
Continued above ground plumbing and roof drain rough
in. |
 |
Completed installation of above ground radon piping. |
 |
Continued above ground roof drain connections. |
|
|

2/11/2004
Structural steel work continues.
|

2/11/2004
Structural steel work continues.
|
2/5/2004
Roofing materials delivered. |
|
Activities completed during the week of January 26,
2004:
 |
Above ground plumbing pipe and roof drain
installation commenced. |
 |
Installation of above ground radon piping commenced. |
|
1/21/2004
Roof drains installed. |
1/21/2004
Above ground plumbing continues to be installed. |
|
Activities completed during the week of January 12,
2004:
 |
Continued above ground plumbing. |
 |
Continued to install roof drains. |
|
Activities completed during the week of January 5,
2004:
 |
Roof pan metal deck openings cut out. |
 |
Continued installation of electrical piping in
existing building. |
|
1/8/2004
Structural work continues on classrooms. |
|

1/8/2004
Structural work continues on gym. |
12/19/2003
Steel and roof decking installed. |
12/19/2003
Roof decking installed on the gymnasium addition. |
|

12/12/2003
Structural steel for gymnasium being installed.
|
12/9/2003
Structural steel and roof decking in the process of being installed. |
12/9/2003
Soil compacted for storm drain. |
|

12/2/2003
Structural steel was erected for future classrooms.
|
12/1/2003
Concrete slab completed for gymnasium. |
12/1/2003
Concrete slab completed for classrooms. |
|

11/21/2003
Final preparations for cement flooring completed.
|
11/21/2003
Sewer waste line installed |
11/13/2003
Stone base for gym completed. |
11/10/2003
Stone base applied for kitchen and gym. |
11/10/2003
Sewer and storm lines installed. |
11/10/2003
Stone base for
gym floor applied. |
11/3/2003
New water main installed. |
11/3/2003
Foundation set. |
11/3/2003
Gymnasium foundation set. |
10/22/2003
Concrete for foundation is poured. |
10/22/2003
Foundation work continues. |
10/22/2003
Emergency exit installed in back of building. |
10/8/2003
Foundation established.
|
10/8/2003
Earthwork continues. |
10/8/2003
Earthwork commences at the main entrance site. |

10/7/2003
Site grading and earthwork commenced.
|

10/7/2003
Silt fence installed.
|
Activities completed during the month
of September:
 |
Site demolition commenced.
|
 |
Site grading and earthwork commenced.
|
 |
Silt fence installed.
|
 |
Gas line relocated.
|
 |
Field office and storage trailers
delivered.
|
 |
Temporary power installed.
|
|
9/22/2003
Gas line relocated.
|
9/22/2003
Area leveled off.
|
9/16/2003
Blacktop removed.
|

9/16/2003
Construction trailer arrives on site. |
9/4/2003
Future site of addition.
|

9/4/2003
Construction fencing erected. |
9/4/2003
Safety paths painted.
|
9/4/2003
New main entrance during construction.
|
9/4/2003
Safety fencing erected.
|