Franklin Elementary School

  Photo Journal will be updated on a regular basis...

Activities completed during  the week of 
November 1,2004:

Worked on paperwork for kitchen permits.

Continued installation of door glazing.

Removed electrical materials.

Patched asphalt driveway.

Completed grading.

Final fire inspection held for both additions.

 

11/11/2004
Media Center is 
stocked and in use!

11/11/2004
New computer lab... 
up and running!

Activities completed during  the week of 
October 11,2004:

Completed base molding for gym floor.

Continued working on programming of ATC controls.

Worked on paperwork for permits for kitchen.

Changed cores for interior doors.

 

10/19/2004
Furniture and books set up in the new Media Center.

10/19/2004
Equipment being installed in the new kitchen.



10/19/2004
Floor sealed in new gymnasium.

10/19/2004
New computer lab completed.

Activities completed during  the week of 
September 6, 2004:

Continued connections of kitchen equipment.

Commenced installation of light fixtures in kitchen.

Completed installation and testing of fire alarm devices.

Completed installation of acoustical ceiling tiles.

Completed installation of interior doors and glazing.

Commenced final  cleaning.

Commenced start-up of classroom Airedale units.

Obtained a Temporary Certificate of Occupancy for Area A classrooms.

9/10/2004
Another small instruction classroom prepared for use.

9/10/2004
Furniture delivered to one of the new small instruction classrooms.

9/10/2004
Main entrance completed.

9/10/2004
Flooring delivered to new gymnasium.

9/10/2004
Completed hallway leading to new classrooms.

9/10/2004
Carpeting laid in Media Center.

9/10/2004
Another classroom completed.

9/10/2004
Furniture delivered to completed Art classroom.

9/10/2004
Classroom completed.

Activities completed during  the week of August 16,2004:

Completed site grading and installation of curbs and sidewalks.

Continued installation of kitchen equipment.

Continued installation of fire alarm devices.

Completed installation of floors in renovated rooms.

Commenced painting rooms.

Completed installation of water heaters in existing boiler room.

Commenced installation of acoustical ceiling tiles.

Transferred permanent power.

8/17/2004
Leveling of ground continues.

8/17/2004
Book shelves assembled for Media Center.

8/17/2004
Dry erase board and bulletin board installed in classroom.

8/17/2004
Shelving and storage cabinet installed in classroom.

8/17/2004
Cabinets and cubbies installed in classroom.

8/17/2004
Basketball hoops installed in gymnasium.

8/17/2004
Exterior work continues on gymnasium.

8/17/2004
Doors to new main entrance are installed.

8/17/2004
Cement poured for sidewalks.

8/17/2004
Exterior work continues on the classroom addition.

Activities completed during the week of June 14, 2004:

Power washed brick on classroom wing.

Continued installation of light fixtures in gym.

Continued installation of ceramic floor tile.

Continued demolition of existing kitchen.

Continued installation of roof system and coping.

Commenced pulling data wire.

6/21/2004
Work on gymnasium wing continues.

6/21/2004
Work on classroom wing continues.

Activities completed during the week of June 7, 2004:

Continued installation of brick in Area B.

Continued installation of light fixtures in both construction areas.

Continued installation of ceramic wall and floor tile.

Continued demolition of existing kitchen.

Pulled secondary feeder wires.

Activities completed during the week of June 1, 2004:

Continued installation of brick in Area B.

Commenced installation of light fixtures in both construction areas.

Continued installation of ceramic wall and floor tile.

Completed painting in classroom wing.

Commenced demolition of existing kitchen.

5/28/2004
Work continues on the interior of the new media center.

5/28/2004
Tile installed in new restroom.

5/28/2004
Classroom HVAC unit delivered.

Activities completed during the week of May 17, 2004:

Power washed brick.

Continued installation of brick on gymnasium wing.

Installed interior HVAC units in new classrooms.

Continued installation of electrical wire and fixtures.

Continued installation of ceramic wall tile in classrooms.

Commenced painting on gymnasium wing.

Activities completed during the week of May 10, 2004:

Continued installation of brick.

Commenced installation of brick on gymnasium area.

Continued mechanical piping in existing mechanical room.

Continued installation of electrical wire and cable trays.

Commenced installation of ceramic wall tile.

5/14/2004
Brick face being installed.

5/14/2004
Exterior block walls completed.

Activities completed during the week of May 3, 2004:

Continued installation of brick.

Complete installation of underground conduit for transformer.

Completed installation of pumps in existing mechanical room.

Continued ductwork in gym and mechanical mezzanine.

Completed flashing at perimeter of roof additions.

Activities completed during the week of 
April 26, 2004:

Commenced installation of brick.

Commenced excavation for power to transformer location.

Completed installation of underground conduit for transformer.

Installed pumps in existing mechanical room.

4/26/2004
Interior work on gymnasium continued.

4/26/2004
Work continues on future hallway.

4/26/2004
Interior work on gymnasium continued.

Activities completed during the week of 
April 12, 2004:

Continued installation of masonry walls.

Completed installation of electrical masonry wall rough-ins.

Poured concrete slab for mezzanine in gym area.

Poured concrete slab on grade for kitchen.

Removed existing glass block in Multi-Purpose Room and installed masonry block. 

Connected new sanitary line to existing area.

Commence pulling wire for devices in classroom area.

Completed installation of mechanical piping in existing corridor. 

 

Activities completed during the week of 
April 5, 2004:

Continued installation of masonry walls.

Continued installation of electrical masonry wall rough-ins.

Completed installation of mechanical piping and duct work in classroom additions.

Completed installation of underground plumbing and underground electric in kitchen area. 

Installed new site pole at corner of gymnasium site.

Activities completed during the week of 
March 29, 2004:

Continued installation of masonry walls.

Continued installation of electrical masonry wall rough-ins.

Continued installation of mechanical ductwork.

Continued installation of mechanical piping.

Commenced installation of underground plumbing in kitchen.

Removed hangover of existing gym.

4/9/2004
Media Center is framed with block walls.

4/9/2004
Exterior walls for gymnasium installed.



4/9/2004
Exterior block walls continue to be installed.


Activities completed during the week of 
March 22, 2004:

Completed installation of masonry walls.

Commenced installation of masonry walls on gymnasium addition.

Completed installation of electrical masonry wall rough-ins.

Commenced installation of electrical masonry wall rough-ins on gymnasium addition.

Continued installation of mechanical ductwork and mechanical piping for classroom additions.

Commenced layout of mechanical ductwork in gymnasium addition.

3/26/2004
Block wall installation continued.

3/19/2004
Masonry walls installed.

Activities completed during the week of 
March 8, 2004:

Continued installation of masonry walls.

Continued installation of electrical masonry wall rough-ins.

Completed installation of domestic water piping insulation.

Installed new Rooftop Unit above mechanical room.

3/15/2004
Work continues on masonry walls.



3/15/2004
Concrete block on site for masonry walls of gymnasium.

 

 

Activities completed during the week of 
February 16, 2004:

Completed installation of roof insulation and tar in Area A.

Commenced installation of roof insulation and tar in Area B.

Continued installation of masonry walls

Continued installation of electrical masonry wall rough-ins.

Completed installation of exhaust fan roof curbs.

Completed installation of wood blocking for roof curbs.

Commenced installation of domestic water piping in chase walls.

2/25/2004
Interior walls installation commenced.

2/25/2004
Workers prepare to install interior walls.

2/20/2004
Roof curbs installed.

2/20/2004
Installation of roof commences.



2/20/2004
Installation of concrete block walls commences.

 

Activities completed during the week of 
February 9, 2004:

Completed above ground plumbing pipe and roof drain.

Completed above ground rood drain connections.

Commenced installation of masonry walls.

Commenced installation of electrical masonry wall rough-ins.

Completed installation of roof curbs.

Commenced installation of exhaust fan roof curbs.

Commenced installation of wood blocking for roof curbs.

Activities completed during the week of 
February 2, 2004:

Continued above ground plumbing and roof drain rough in.

Completed installation of above ground radon piping.

Continued above ground roof drain connections.



2/11/2004
Structural steel work continues.



2/11/2004
Structural steel work continues.

2/5/2004
Roofing materials delivered.

Activities completed during the week of January 26, 2004:

Above ground plumbing pipe and roof drain installation commenced.

Installation of above ground radon piping commenced.

 

1/21/2004
Roof drains installed.

1/21/2004
Above ground plumbing continues to be installed.



Activities completed during the week of January 12, 2004:

Continued above ground plumbing.

Continued to install roof drains.

 

Activities completed during the week of January 5, 2004:

Roof pan metal deck openings cut out.

Continued installation of electrical piping in existing building.

 

1/8/2004
Structural work continues on classrooms.

1/8/2004
Structural work continues on gym.

12/19/2003
Steel and roof decking installed.

12/19/2003
Roof decking installed on the gymnasium addition.

12/12/2003
Structural steel for gymnasium being installed.

12/9/2003
Structural steel and roof decking in the process of being installed.

12/9/2003
Soil compacted for storm drain.

12/2/2003
Structural steel was erected for future classrooms.

12/1/2003
Concrete slab completed for gymnasium.

12/1/2003
Concrete slab completed for classrooms.

11/21/2003
Final preparations for cement flooring completed.

11/21/2003
Sewer waste line installed

11/13/2003
Stone base for gym completed.

11/10/2003
Stone base applied for kitchen and gym.

11/10/2003
Sewer and storm lines installed.

11/10/2003
Stone base for 
gym floor applied.

11/3/2003
New water main installed.

11/3/2003
Foundation set.

11/3/2003
Gymnasium foundation set.

10/22/2003
Concrete for foundation is poured.

10/22/2003
Foundation work continues.

10/22/2003
Emergency exit installed in back of building.

10/8/2003
Foundation established.

10/8/2003
Earthwork continues.

10/8/2003
Earthwork commences at the main entrance site.

10/7/2003
Site grading and earthwork commenced.

10/7/2003
Silt fence installed.

Activities completed during the month of September:

Site demolition commenced.

Site grading and earthwork commenced.

Silt fence installed.

Gas line relocated.

Field office and storage trailers delivered.

Temporary power installed.

9/22/2003
Gas line relocated.

 

9/22/2003
Area leveled off.

9/16/2003
Blacktop removed.

9/16/2003
Construction trailer arrives on site.

 

9/4/2003
Future site of addition.

9/4/2003
Construction fencing erected.

9/4/2003
Safety paths painted.

 

9/4/2003
New main entrance during construction.

9/4/2003
Safety fencing erected.

FRANKLIN SCHOOL
Roxbury Township Public Schools
8 Meeker Street
Succasunna, NJ 07876

(973) 584-5549   Fax (973) 252-1151
 

January 8, 2005

 Dear Parents,

HOORAY!  Our kitchen facility is completed and ready for use.  Hot lunches will be served beginning Monday, January 10th.  Menus for the month were sent home with students last Friday.  We will continue to offer “Jack’s Pizza” on the 2nd and 4th Friday of every month because it was so popular with the children (and parents!)

 Our new gymnasium is being used for physical education classes but cannot yet be used by outside groups until we receive a permanent Certificate of Occupancy.  There are some construction items that need to be attended to and until they are completed, we cannot open the facility to the general public.  We will notify you when we have the permanent certificate.

 Our Ribbon Cutting Ceremony will be scheduled soon and information about that event will be posted on our regular school site.  Flyers will be sent home with the students indicating the date, time, and room location.  It is likely to take place at the end of January or early February.  Stay tuned…..

 Lastly, I would like to thank the Franklin School parents for their unwavering support and patience throughout this building project.  You have been absolutely wonderful waiting for various phases of construction to be completed.  We can now all agree that it was worth the wait!

Sincerely,

 Mary Ann Boyd

Principal